Contractor shall provide all labor, materials, equipment, supervision, and all other resources necessary to construct per plans and specifications project 550-15-107, remediate legionella station-wide PHASE-1. The scope of this project is to replace the domestic water distribution system in building 58 and to install a continuous water monitoring ...show moreContractor shall provide all labor, materials, equipment, supervision, and all other resources necessary to construct per plans and specifications project 550-15-107, remediate legionella station-wide PHASE-1. The scope of this project is to replace the domestic water distribution system in building 58 and to install a continuous water monitoring system in buildings 39, 58, 101, 103, 128, 129, 130 and 131.
VISN 12: Great Lakes Health Care System
No anomaly signals triggered on this contract.
Number of Bidders: Not reported
Extent Competed: Not reported
Solicitation Procedures: Not reported
Business Size: Not reported
No modifications recorded.